Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Interfering float Free float Total float Duration Interfering float Free float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % 0.5 Less than 50 % 1 More than 50 % 0.5 Less than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Maximum Minimum Infinite Zero Maximum Minimum Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour All listed here Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey ANSWER DOWNLOAD EXAMIANS APP