Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Interfering float Total float Duration Free float Interfering float Total float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Minimum Infinite Zero Maximum Minimum Infinite Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials All listed here Availability of labour Site survey Availability of construction materials All listed here Availability of labour Site survey ANSWER DOWNLOAD EXAMIANS APP