Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Duration Interfering float Free float Total float Duration Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 0.5 More than 50 % Less than 50 % 1 0.5 More than 50 % Less than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Minimum Zero Infinite Maximum Minimum Zero Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey ANSWER DOWNLOAD EXAMIANS APP