Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Total float Free float Interfering float Duration Total float Free float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Site located The invitations are being sent Foundation is being dug The office area is being cleaned Site located The invitations are being sent Foundation is being dug The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Issue of store equipments Names of the casual labour Construction measurements Instructions by the executive engineers Issue of store equipments Names of the casual labour Construction measurements Instructions by the executive engineers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis ANSWER DOWNLOAD EXAMIANS APP