Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Duration Free float Interfering float Total float Duration Free float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An activity Both event and activity An event None of these An activity Both event and activity An event None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Excavation for foundation Setting of question paper All listed here Curing of concrete Excavation for foundation Setting of question paper All listed here Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 3425 kg 5515 kg 4350 kg 2975 kg 3425 kg 5515 kg 4350 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP