Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Interfering float Total float Free float Duration Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Any of the above More than X Equal to X Less than X Any of the above More than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these The particular activity involved Succeeding activities Preceding activities None of these The particular activity involved Succeeding activities Preceding activities ANSWER DOWNLOAD EXAMIANS APP