Construction Planning and Management A construction schedule is prepared after collecting Output of labour Output of machinery All listed here Number of operations Output of labour Output of machinery All listed here Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D LS = LF - D EF = ES + D All listed here LF = LS + D LS = LF - D EF = ES + D All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Duration Constraint Float Event Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 19 days 13 days 9 days 14 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP