Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started All listed here Laying of concrete started Digging of foundation completed Digging of foundation started All listed here Laying of concrete started Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Is built of activities oriented programme Is based on time estimate Synthesising in concepts All listed here Is built of activities oriented programme Is based on time estimate Synthesising in concepts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP