Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started All listed here Digging of foundation completed Laying of concrete started Digging of foundation started All listed here Digging of foundation completed Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP