Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation started All listed here Digging of foundation completed Laying of concrete started Digging of foundation started All listed here Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Clam shell Dump truck Bulldozer Scraper Clam shell Dump truck Bulldozer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 6,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 8,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP