Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Free float Event Dummy Constraint Free float Event Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these Project progress ANSWER DOWNLOAD EXAMIANS APP