Construction Planning and Management
Free float for any activity is defined as the difference between

its earliest finish time and latest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its latest finish time and earliest start time for its successor activity
its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float of the activity must be zero but independent float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Independent float must be zero but free float need not be zero

ANSWER DOWNLOAD EXAMIANS APP