Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed Digging of foundation started All listed here Laying of concrete started Digging of foundation completed Digging of foundation started All listed here Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Event Free float Dummy Constraint Event Free float Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP