Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 10 days 9 days 8 days 15 days 10 days 9 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 85 and 75 90 and 80 75 and 83 80 and 90 85 and 75 90 and 80 75 and 83 80 and 90 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP