Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Less than X Any of the above Equal to X More than X Less than X Any of the above Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP