Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 7,600 Rs. 8,800 Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 Rs. 6,400 Rs. 5,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 2975 kg 3425 kg 5515 kg 4350 kg 2975 kg 3425 kg 5515 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 24 None of these 19 14 24 None of these 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling ANSWER DOWNLOAD EXAMIANS APP