Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Engineer Assistant Engineer Junior Engineer Executive Engineer Engineer Assistant Engineer Junior Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Zero Minimum Infinite Maximum Zero Minimum Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 54 36 81 9 54 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest May be longest May be shortest ANSWER DOWNLOAD EXAMIANS APP