Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project All listed here Major projects Minor projects Any project All listed here Major projects Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Chief Engineer Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer Executive Engineer Superintending Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 35 15 20 25 35 15 20 ANSWER DOWNLOAD EXAMIANS APP