Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Independent float Total float Free float Interfering float Independent float Total float Free float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Foundation is being dug The invitations are being sent Site located The office area is being cleaned Foundation is being dug The invitations are being sent Site located The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP