Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum time Minimum cost Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling Updating ANSWER DOWNLOAD EXAMIANS APP