Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency All listed here Separation of planning and design part Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If not symmetrical, are called skew curves If symmetrical, are called normal curves All listed here Having a single lump, are called uninodal curves If not symmetrical, are called skew curves If symmetrical, are called normal curves All listed here Having a single lump, are called uninodal curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority Effective control at all levels All listed here Unity of command Delegation of authority Effective control at all levels All listed here Unity of command ANSWER DOWNLOAD EXAMIANS APP