Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 37950 Rs. 50000 Rs. 34500 Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 Rs. 31050 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 15 35 25 20 15 35 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.5 1 0.841 0.999 0.5 1 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Curing of concrete Excavation for foundation All listed here Setting of question paper Curing of concrete Excavation for foundation All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of machinery All listed here Output of labour Number of operations Output of machinery All listed here Output of labour Number of operations ANSWER DOWNLOAD EXAMIANS APP