Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Kneading Pressing Vibration Tamping Kneading Pressing Vibration Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Succeeding activities The particular activity involved Preceding activities None of these Succeeding activities The particular activity involved Preceding activities None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Dump truck Scraper Bulldozer Clam shell Dump truck Scraper Bulldozer Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources Preparation of estimates All listed here Preparation of specifications Initiating the procurement action of resources Preparation of estimates All listed here Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP