Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Event Connector Node All listed here Event Connector Node All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Zero Same Positive Negative Zero Same Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Moist loam Well blasted rock Wet sticky clay Good common earth Moist loam Well blasted rock Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP