Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An owner An architect An engineer All listed here An owner An architect An engineer All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Crash time Standard time Slow time Normal time Crash time Standard time Slow time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Zero float Minimum float None of these Maximum float Zero float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of profit and loss Economics of cost and benefits of the project Change in output due to change in input Comparison of assets and liabilities Comparison of profit and loss Economics of cost and benefits of the project Change in output due to change in input Comparison of assets and liabilities ANSWER DOWNLOAD EXAMIANS APP