Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Total float Interfering float Independent float Free float Total float Interfering float Independent float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Shaping and trimming Finishing, shaping and trimming Finishing and shaping Trimming and finishing Shaping and trimming Finishing, shaping and trimming Finishing and shaping Trimming and finishing ANSWER DOWNLOAD EXAMIANS APP