Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 80 and 90 75 and 83 85 and 75 90 and 80 80 and 90 75 and 83 85 and 75 ANSWER DOWNLOAD EXAMIANS APP