Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Research and development projects Deterministic activities Large and complex projects Small projects Research and development projects Deterministic activities Large and complex projects Small projects ANSWER DOWNLOAD EXAMIANS APP