Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Site survey All listed here Availability of labour Availability of construction materials Site survey All listed here Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in neither of the two projects should invest in project A could invest in either of the two projects should invest in project B should invest in neither of the two projects should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 ANSWER DOWNLOAD EXAMIANS APP