Construction Planning and Management While filling the tender for any work, the contractor considers Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 4350 kg 5515 kg 2975 kg 3425 kg 4350 kg 5515 kg 2975 kg 3425 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 30 kg 900 kg 1000 kg 300 kg 30 kg 900 kg 1000 kg 300 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Least cost slope Shortest duration Highest cost slope Longest duration Least cost slope Shortest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP