Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 13 days 14 days 9 days 19 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Number of operations All listed here Output of machinery Output of labour Number of operations All listed here Output of machinery Output of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Initiation of proposal Preparation of estimate Survey of the site Preparation of tender Initiation of proposal Preparation of estimate Survey of the site ANSWER DOWNLOAD EXAMIANS APP