Construction Planning and Management The first stage of a construction, is Initiation of proposal Preparation of tender Preparation of estimate Survey of the site Initiation of proposal Preparation of tender Preparation of estimate Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 20 15 35 25 20 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Connector Node All listed here Event Connector Node All listed here Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 12500 kg 22500 kg 10000 kg 5000 kg 12500 kg 22500 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP