Construction Planning and Management The first stage of a construction, is Preparation of tender Initiation of proposal Preparation of estimate Survey of the site Preparation of tender Initiation of proposal Preparation of estimate Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 80 and 90 90 and 80 85 and 75 75 and 83 80 and 90 90 and 80 85 and 75 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Unity of command Delegation of authority Effective control at all levels All listed here Unity of command Delegation of authority Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Longest duration Shortest duration Highest cost slope Least cost slope Longest duration Shortest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Positive Zero Negative Same Positive Zero Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP