Construction Planning and Management Which of the following excavators is most suitable for digging under water? Hoe Drag line Clam shell Dipper shovel Hoe Drag line Clam shell Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP