Construction Planning and Management Which of the following excavators is most suitable for digging under water? Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Minimum Maximum Zero Infinite Minimum Maximum Zero Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these Succeeding activities Preceding activities The particular activity involved None of these Succeeding activities Preceding activities The particular activity involved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 0.5 Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Concrete Ice Loose sand Earth Concrete Ice Loose sand Earth ANSWER DOWNLOAD EXAMIANS APP