Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 90 and 80 80 and 90 85 and 75 75 and 83 90 and 80 80 and 90 85 and 75 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 3 1 4 2 3 1 4 ANSWER DOWNLOAD EXAMIANS APP