Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 2975 kg 3425 kg 4350 kg 5515 kg 2975 kg 3425 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent The office area is being cleaned Site located Foundation is being dug The invitations are being sent The office area is being cleaned Site located Foundation is being dug ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Bar chart method Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP