Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is A person An agency A firm All listed here A person An agency A firm All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 22500 kg 12500 kg 10000 kg 5000 kg 22500 kg 12500 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest May be longest ANSWER DOWNLOAD EXAMIANS APP