Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Crash time Optimistic time Normal time Between normal time and crash time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Event flow scheduling technique Critical ratio scheduling Short interval scheduling Slotting technique for scheduling Event flow scheduling technique Critical ratio scheduling Short interval scheduling Slotting technique for scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP