Construction Planning and Management The time corresponding to minimum total project cost is Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 90 and 80 80 and 90 85 and 75 75 and 83 90 and 80 80 and 90 85 and 75 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of assets and liabilities Change in output due to change in input Comparison of profit and loss Economics of cost and benefits of the project Comparison of assets and liabilities Change in output due to change in input Comparison of profit and loss Economics of cost and benefits of the project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Highest cost slope Longest duration Least cost slope Shortest duration Highest cost slope Longest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP