Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Between normal time and crash time Normal time Crash time Optimistic time Between normal time and crash time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 3.5 and 25/36 5 and 25/36 4 and 5/6 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 9 days 13 days 19 days 14 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Negative Zero Same Positive Negative Zero Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Economics of cost and benefits of the project Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input Economics of cost and benefits of the project Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP