Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Crash time Normal time Optimistic time Between normal time and crash time Crash time Normal time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time Pessimistic time Most likely time All listed here Optimistic time Pessimistic time Most likely time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves Having a single lump, are called uninodal curves If not symmetrical, are called skew curves If symmetrical, are called normal curves All listed here Having a single lump, are called uninodal curves If not symmetrical, are called skew curves If symmetrical, are called normal curves All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured ANSWER DOWNLOAD EXAMIANS APP