Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Class is being attended Bus starts from Jaipur Sessional work completed Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 25 35 20 15 25 35 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP