Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 50000 Rs. 31050 Rs. 37950 Rs. 34500 Rs. 50000 Rs. 31050 Rs. 37950 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities ANSWER DOWNLOAD EXAMIANS APP