Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For all activities required to start the work at site on finalization of the contract document
For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of both activities A and B are same
None of these
expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

Both A and R is true and R is the correct explanation of A
A is false but R is true
A is true but R is false
Both A and R is true but R is not the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP