Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect An owner All listed here An engineer An architect An owner All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Event Constraint Float Duration Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 ANSWER DOWNLOAD EXAMIANS APP