Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 12500 kg 5000 kg 22500 kg 10000 kg 12500 kg 5000 kg 22500 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Positive Same Negative Zero Positive Same Negative ANSWER DOWNLOAD EXAMIANS APP