Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the purchase of construction materials
For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
On all the activities lying on the critical path
On all the activities

ANSWER DOWNLOAD EXAMIANS APP