Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Concrete Loose sand Earth Ice Concrete Loose sand Earth Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Zero Minimum Infinite Maximum Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Economics of cost and benefits of the project Change in output due to change in input Comparison of assets and liabilities Comparison of profit and loss Economics of cost and benefits of the project Change in output due to change in input Comparison of assets and liabilities Comparison of profit and loss ANSWER DOWNLOAD EXAMIANS APP