Construction Planning and Management
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is

1, 3, 2, 4
1, 3, 4, 2
3, 1, 4, 2
3, 1, 2, 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and increasing indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP