Construction Planning and Management
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is

1, 3, 2, 4
3, 1, 2, 4
1, 3, 4, 2
3, 1, 4, 2

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the purchase of construction materials
On commencement of work at site for payment of loan taken by him
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP