Construction Planning and Management
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is

3, 1, 2, 4
1, 3, 2, 4
1, 3, 4, 2
3, 1, 4, 2

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

less than latest event time of preceding node
equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP