Construction Planning and Management
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is

3, 1, 2, 4
1, 3, 2, 4
3, 1, 4, 2
1, 3, 4, 2

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Rate of inflation
Increase in rates of only important materials
Variation in total cost of the project on an ad hoc basis
Variation in cost in materials element, labour element and petrol-oil-lubricant element