Construction Planning and Management
Preliminary project report for a road project must contain

The contract documents for inviting tenders
The soil survey, traffic survey, concept design and approximate cost
The several alternatives of the project that have been considered
The detailed estimated cost based on detailed design

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
less than latest event time of preceding node
equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Controlling the quantity of each material into each batch
Controlling the total quantity at each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Weighing accurately, the quantity of each material for a job before mixing

ANSWER DOWNLOAD EXAMIANS APP