Construction Planning and Management Batching refers to Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here LF = LS + D LS = LF - D EF = ES + D All listed here LF = LS + D LS = LF - D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 54 36 81 9 54 36 ANSWER DOWNLOAD EXAMIANS APP