Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart All listed here Modified Mile stone chart Bar chart Gantt chart All listed here Modified Mile stone chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 2 kg/tonne 20 kg/tonne 9 kg/tonne 6 kg/tonne 2 kg/tonne 20 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1910 1920 1930 1940 1910 1920 1930 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The office area is being cleaned Site located The invitations are being sent Foundation is being dug The office area is being cleaned Site located The invitations are being sent Foundation is being dug ANSWER DOWNLOAD EXAMIANS APP