Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Event Connector Node All listed here Event Connector Node All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of excavation which takes 8 units of time Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of excavation which takes 8 units of time Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP