Construction Planning and Management Time and progress chart of a construction, is also known as Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Pessimistic time All listed here Optimistic time Most likely time Pessimistic time All listed here Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 4 2 3 1 4 2 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Infinite Zero Minimum Maximum Infinite Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 10000 kg 12500 kg 22500 kg 5000 kg 10000 kg 12500 kg 22500 kg ANSWER DOWNLOAD EXAMIANS APP