Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 8,75,000 Rs. 10,50,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 8,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.999 0.5 1 0.841 0.999 0.5 1 ANSWER DOWNLOAD EXAMIANS APP