Construction Planning and Management Time and progress chart of a construction, is also known as Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Construction measurements Issue of store equipments Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments Instructions by the executive engineers Names of the casual labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne ANSWER DOWNLOAD EXAMIANS APP