Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Modified Mile stone chart All listed here Bar chart Gantt chart Modified Mile stone chart All listed here Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 4 2 3 1 4 2 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials All listed here Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 16 days 10 days 6 days 4 days 16 days 10 days 6 days ANSWER DOWNLOAD EXAMIANS APP