Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An activity An event Both event and activity None of these An activity An event Both event and activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Decrease of project completion time All of these Increase of project completion time Change of critical path Decrease of project completion time All of these Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 None of these 24 14 19 None of these 24 ANSWER DOWNLOAD EXAMIANS APP