Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest May be shortest Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.5 1 0.999 0.841 0.5 1 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP