Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command All listed here Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Loose sand Concrete Firm earth Asphalt Loose sand Concrete Firm earth Asphalt ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Positive Negative Zero Same Positive Negative Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP