Construction Planning and Management Time and progress chart of a construction, is also known as Bar chart Gantt chart All listed here Modified Mile stone chart Bar chart Gantt chart All listed here Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 15 minutes 21 minutes 20.143 minutes 27 minutes 15 minutes 21 minutes 20.143 minutes 27 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest critical activity Costliest critical activity Cheapest noncritical activity Costliest noncritical activity Cheapest critical activity Costliest critical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP