Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Modified Mile stone chart Bar chart All listed here Gantt chart Modified Mile stone chart Bar chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Line and staff organization Functional organization Line organization None of these Line and staff organization Functional organization Line organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP