Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its latest finish time and earliest start time for its successor activity
its earliest finish time and latest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP