Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Bar chart Gantt chart Modified Mile stone chart All listed here Bar chart Gantt chart Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 8,800 Rs. 7,600 Rs. 5,000 Rs. 6,400 Rs. 8,800 Rs. 7,600 Rs. 5,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is false but R is true A is true but R is false Both A and R is true and R is the correct explanation of A Both A and R is true but R is not the correct explanation of A A is false but R is true A is true but R is false Both A and R is true and R is the correct explanation of A Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 1 0.5 More than 50 % Less than 50 % 1 0.5 More than 50 % ANSWER DOWNLOAD EXAMIANS APP