Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Normal durations for all the activities
Crash durations for all activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
A part of the money kept in reserve for providing additional structures and structural modifications

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its earliest finish time and latest start time for its successor activity
its latest start time and earliest start time
its earliest finish time and earliest start time for its successor activity
its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP