Construction Planning and Management Time and progress chart of a construction, is also known as Bar chart All listed here Gantt chart Modified Mile stone chart Bar chart All listed here Gantt chart Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Bulldozer Clam shell Dump truck Scraper Bulldozer Clam shell Dump truck Scraper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 15 days 9 days 8 days 10 days 15 days 9 days ANSWER DOWNLOAD EXAMIANS APP