Construction Planning and Management Updating may result in Change of critical path All of these Increase of project completion time Decrease of project completion time Change of critical path All of these Increase of project completion time Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 4350 kg 3425 kg 2975 kg 5515 kg 4350 kg 3425 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP