Construction Planning and Management Updating may result in All of these Change of critical path Increase of project completion time Decrease of project completion time All of these Change of critical path Increase of project completion time Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 8 days 10 days 9 days 15 days 8 days 10 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 50 kg/tonne 30 kg/tonne 20 kg/tonne 40 kg/tonne 50 kg/tonne 30 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Moist loam Sand and gravel Wet sticky clay Good common earth Moist loam Sand and gravel Wet sticky clay Good common earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 4350 kg 3425 kg 2975 kg 5515 kg 4350 kg 3425 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 None of these 24 19 14 None of these 24 19 ANSWER DOWNLOAD EXAMIANS APP