Construction Planning and Management
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iv) are correct
(i) and (iii) are correct
(ii) and (iv) are correct
(ii) and (iii) are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same
expected time of activity B is greater than the expected time of activity A
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP