Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 9 days 10 days 8 days 15 days 9 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource smoothening Resource levelling Critical path scheduling Updating Resource smoothening Resource levelling Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP