Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is based on time estimate Is built of activities oriented programme All listed here Synthesising in concepts Is based on time estimate Is built of activities oriented programme All listed here Synthesising in concepts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Equal to X Any of the above Less than X More than X Equal to X Any of the above Less than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Is a dynamic system None of these Determines the status of each activity Adjusts automatically changes in activity progress Is a dynamic system None of these Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Event Constraint Free float Dummy Event Constraint Free float ANSWER DOWNLOAD EXAMIANS APP