Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 2 kg/tonne 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne 6 kg/tonne 9 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 14 days 19 days 13 days 9 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 10 days 8 days 9 days 15 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP