Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Highest cost slope Shortest duration Longest duration Least cost slope Highest cost slope Shortest duration Longest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 3480 Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 Rs. 1740 Rs. 6960 Rs. 5220 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP