Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Least cost slope Shortest duration Highest cost slope Longest duration Least cost slope Shortest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 22500 kg 5000 kg 12500 kg 10000 kg 22500 kg 5000 kg 12500 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Normal distribution curve Poisson's distribution curve None of these Beta distribution curve Normal distribution curve Poisson's distribution curve None of these Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP