Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 15 days 8 days 9 days 10 days 15 days 8 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve Normal distribution curve Beta distribution curve None of these Poisson's distribution curve Normal distribution curve Beta distribution curve None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.841 1 0.5 0.999 0.841 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Maximum Minimum Infinite Zero Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP