Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Light construction None of these Heavy construction Industrial construction Light construction None of these Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Standard time Slow time Crash time Normal time Standard time Slow time Crash time ANSWER DOWNLOAD EXAMIANS APP