Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Standard time Crash time Slow time Normal time Standard time Crash time Slow time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP