Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Standard time Normal time Slow time Crash time Standard time Normal time Slow time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float None of these Minimum float Zero float Maximum float None of these Minimum float Zero float ANSWER DOWNLOAD EXAMIANS APP