Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

Yes, because of heavier overheads and handling cost
No, because of repetitive manufacture of a number of elements
Yes, because of the very high order of quality control for the factory made components
No, because of savings in site labour

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
For the purchase of construction materials
On commencement of work at site for payment of loan taken by him
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iii) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
(i) and (iv) are correct