Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 3 2 1 4 3 2 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Zero Same Negative Positive Zero Same Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 81 36 54 9 81 36 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Any of the above Less than X Equal to X More than X Any of the above Less than X Equal to X ANSWER DOWNLOAD EXAMIANS APP