Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Industrial construction Light construction Heavy construction Electrical construction Industrial construction Light construction Heavy construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Most likely time Optimistic time All listed here Pessimistic time Most likely time Optimistic time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs ANSWER DOWNLOAD EXAMIANS APP