Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 12500 kg 22500 kg 5000 kg 10000 kg 12500 kg 22500 kg 5000 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest May be longest May be shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known All listed here Connector Event Node All listed here Connector Event Node ANSWER DOWNLOAD EXAMIANS APP