Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 None of these 14 19 24 None of these 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Independent float Total float Interfering float Free float Independent float Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Any of the above More than X Equal to X Less than X Any of the above More than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum time Maximum time Maximum cost Minimum cost Minimum time Maximum time Maximum cost Minimum cost ANSWER DOWNLOAD EXAMIANS APP