Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Dragline Hoe None of these Shovel Dragline Hoe None of these Shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Light construction Industrial construction Heavy construction None of these Light construction Industrial construction Heavy construction None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity Costliest noncritical activity Cheapest critical activity Cheapest noncritical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP