Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is All listed here A person An agency A firm All listed here A person An agency A firm ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 None of these 19 24 14 None of these 19 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Horizontal lines Vertical lines Dots Crosses Horizontal lines Vertical lines Dots Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Industrial construction Heavy construction Light construction Electrical construction Industrial construction Heavy construction Light construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP