Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Node Event Connector All listed here Node Event Connector All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Superintending Engineer Executive Engineer Chief Engineer Assistant Engineer Superintending Engineer Executive Engineer Chief Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP