Construction Planning and Management
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

1
0.5
Less than 50 %
More than 50 %

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth.
(iv) Output can be increased by increasing the size of shovel.

(i), (iii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (ii) and (iv) are correct
(i) and (iv) are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP