Construction Planning and Management
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

1
More than 50 %
Less than 50 %
0.5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

ANSWER DOWNLOAD EXAMIANS APP