Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities All of these Uncertainties Project progress Interdependencies of activities All of these Uncertainties Project progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 75 and 83 85 and 75 80 and 90 90 and 80 75 and 83 85 and 75 80 and 90 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 0.999 1 0.5 0.841 0.999 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer All listed here An owner An architect An engineer All listed here An owner An architect ANSWER DOWNLOAD EXAMIANS APP