Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 1 More than 50 % 0.5 Less than 50 % 1 More than 50 % 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An architect All listed here An engineer An owner An architect All listed here An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Minimum Infinite Maximum Zero Minimum Infinite Maximum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Site located Foundation is being dug The invitations are being sent The office area is being cleaned Site located Foundation is being dug The invitations are being sent The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP