Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 Less than 50 % 0.5 More than 50 % 1 Less than 50 % 0.5 More than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Delegation of authority All listed here Effective control at all levels Unity of command Delegation of authority All listed here Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects Minor projects All listed here Any project Major projects Minor projects All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 300 kg 900 kg 1000 kg 30 kg 300 kg 900 kg 1000 kg 30 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Constraint Float Duration Event Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP