Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Bulldozer Dump truck Scraper Clam shell Bulldozer Dump truck Scraper Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Short interval scheduling Slotting technique for scheduling Event flow scheduling technique Critical ratio scheduling Short interval scheduling Slotting technique for scheduling Event flow scheduling technique Critical ratio scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP