Construction Planning and Management
A golden rule for the procurement of construction stones, suggests

100% at the site
50% at the site and 50% under procurement
67% at the site and 33% under procurement
33% at the site and 67% under procurement

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
None of these
expected time of both activities A and B are same

ANSWER DOWNLOAD EXAMIANS APP