Construction Planning and Management
Free float is mainly used to

Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity