Construction Planning and Management A CPM family includes All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Moist loam Wet sticky clay Sand and gravel Good common earth Moist loam Wet sticky clay Sand and gravel Good common earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Interfering float Free float Total float Independent float Interfering float Free float Total float Independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1930 1910 1920 1940 1930 1910 1920 ANSWER DOWNLOAD EXAMIANS APP