Construction Planning and Management A CPM family includes MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Interfering float Free float Total float Independent float Interfering float Free float Total float Independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 5,000 Rs. 8,800 Rs. 6,400 Rs. 7,600 Rs. 5,000 Rs. 8,800 Rs. 6,400 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Loose sand Asphalt Firm earth Concrete Loose sand Asphalt Firm earth Concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity ANSWER DOWNLOAD EXAMIANS APP