Construction Planning and Management A CPM family includes CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 34500 Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 Rs. 31050 Rs. 37950 Rs. 50000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 50000 Rs. 34500 Rs. 37950 Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 Rs. 31050 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP