Construction Planning and Management Interfering float is the difference between None of these Total float and free float Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 13 days 9 days 19 days 14 days 13 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Minimum Infinite Zero Maximum Minimum Infinite Zero Maximum ANSWER DOWNLOAD EXAMIANS APP