Construction Planning and Management Interfering float is the difference between Total float and free float Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Excavation for foundation Curing of concrete All listed here Setting of question paper Excavation for foundation Curing of concrete All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Minimum float Zero float None of these Maximum float Minimum float Zero float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 10 days 16 days 6 days 4 days 10 days 16 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Zero Same Negative Positive Zero Same Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Large and complex projects Small projects Research and development projects Deterministic activities Large and complex projects Small projects Research and development projects Deterministic activities ANSWER DOWNLOAD EXAMIANS APP