Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X Any of the above More than X Less than X Equal to X Any of the above More than X Less than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress None of these Is a dynamic system Determines the status of each activity Adjusts automatically changes in activity progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Names of the casual labour Instructions by the executive engineers Issue of store equipments Construction measurements Names of the casual labour Instructions by the executive engineers Issue of store equipments Construction measurements ANSWER DOWNLOAD EXAMIANS APP