Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 2 4 3 1 2 4 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects Any project All listed here Major projects Minor projects Any project All listed here Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 8 days 15 days 9 days 10 days 8 days 15 days 9 days ANSWER DOWNLOAD EXAMIANS APP