Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (ii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (iii) are correct (i) and (ii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 1500 cum 500 cum 2000 cum 1000 cum 1500 cum 500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 4.23 years 7.87 years 3.7 years 5 years 4.23 years 7.87 years 3.7 years 5 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP