Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Plastering of walls Selecting sites Concrete cured Fixing of door Plastering of walls Selecting sites Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Shovel None of these Dragline Hoe Shovel None of these Dragline Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties Interdependencies of activities All of these Project progress Uncertainties Interdependencies of activities All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP