Construction Planning and Management Interfering float is the difference between Total float and free float Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An event An activity Both event and activity None of these An event An activity Both event and activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects Any project All listed here Minor projects Major projects Any project All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method ANSWER DOWNLOAD EXAMIANS APP