Construction Planning and Management Interfering float is the difference between Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A None of these expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Unity of command Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications ANSWER DOWNLOAD EXAMIANS APP