Construction Planning and Management Interfering float is the difference between Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 9 days 15 days 8 days 10 days 9 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Infinite Maximum Minimum Zero Infinite Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 9 days 19 days 13 days 14 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP