Construction Planning and Management Interfering float is the difference between Total float and free float Free float and independent float None of these Total float and independent float Total float and free float Free float and independent float None of these Total float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Horizontal lines Vertical lines Dots Crosses Horizontal lines Vertical lines Dots ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP