Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Equal to X Less than X Any of the above More than X Equal to X Less than X Any of the above ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 13 days 14 days 9 days 19 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of estimate Preparation of tender Initiation of proposal Survey of the site Preparation of estimate Preparation of tender Initiation of proposal Survey of the site ANSWER DOWNLOAD EXAMIANS APP