Construction Planning and Management
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

Rs. 50000
Rs. 31050
Rs. 37950
Rs. 34500

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Measurement of risks to eliminate failures
Reduction in costs for the removal of defects

ANSWER DOWNLOAD EXAMIANS APP