Construction Planning and Management Mile Stone charts were invented in the year of 1920 1930 1940 1910 1920 1930 1940 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 9 days 14 days 13 days 19 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Positive Same Zero Negative Positive Same Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line organization Functional organization Line and staff organization None of these Line organization Functional organization Line and staff organization None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP