Construction Planning and Management Mile Stone charts were invented in the year of 1940 1930 1920 1910 1940 1930 1920 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 10 days 15 days 8 days 9 days 10 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always longest Is always shortest May be shortest May be longest Is always longest Is always shortest May be shortest May be longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 14 days 19 days 9 days 13 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP