Construction Planning and Management Critical path method All listed here Is an improvement upon bar chart method Provides a realistic approach to daily problems Avoids delays which are very common in bar charts All listed here Is an improvement upon bar chart method Provides a realistic approach to daily problems Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 20 kg/tonne 2 kg/tonne 9 kg/tonne 6 kg/tonne 20 kg/tonne 2 kg/tonne 9 kg/tonne 6 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart Modified Mile stone chart All listed here Gantt chart Bar chart Modified Mile stone chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 4,75,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 9 days 15 days 8 days 10 days 9 days 15 days ANSWER DOWNLOAD EXAMIANS APP