Construction Planning and Management Critical path method Provides a realistic approach to daily problems Is an improvement upon bar chart method All listed here Avoids delays which are very common in bar charts Provides a realistic approach to daily problems Is an improvement upon bar chart method All listed here Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Interfering float Duration Free float Total float Interfering float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time Resources None of these Project duration time Both resources and project duration time Resources None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP