Construction Planning and Management Critical path method All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP