Construction Planning and Management
Critical path method

Provides a realistic approach to daily problems
All listed here
Is an improvement upon bar chart method
Avoids delays which are very common in bar charts

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of both activities A and B are same
None of these
expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP