Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Event Connector All listed here Node Event Connector All listed here Node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of labour All listed here Output of machinery Number of operations Output of labour All listed here Output of machinery Number of operations ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Constraint Duration Event Float Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Any of the above More than X Equal to X Less than X Any of the above More than X Equal to X ANSWER DOWNLOAD EXAMIANS APP