Construction Planning and Management
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

to + 4tm+ tp/5
to + 4tm+ tp/6
to + 3tm+ tp/3
to + 4tm+ tp/4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities which can be delayed without affecting the total float of preceding activity

ANSWER DOWNLOAD EXAMIANS APP