Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/4 to + 4tm+ tp/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Vibration Kneading Tamping Pressing Vibration Kneading Tamping Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An architect All listed here An engineer An owner An architect All listed here An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Standard time Slow time Crash time Normal time Standard time Slow time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete ANSWER DOWNLOAD EXAMIANS APP