Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Grader is used mainly for Finishing, shaping and trimming Shaping and trimming Finishing and shaping Trimming and finishing Finishing, shaping and trimming Shaping and trimming Finishing and shaping Trimming and finishing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 10 days 9 days 8 days 15 days 10 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels Unity of command ANSWER DOWNLOAD EXAMIANS APP