Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/5 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Firm earth Loose sand Concrete Asphalt Firm earth Loose sand Concrete Asphalt ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these Succeeding activities Preceding activities The particular activity involved None of these Succeeding activities Preceding activities The particular activity involved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % 0.5 Less than 50 % 1 More than 50 % 0.5 Less than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum cost Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP