Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Light construction Industrial construction None of these Heavy construction Light construction Industrial construction None of these Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments Instructions by the executive engineers Names of the casual labour Construction measurements Issue of store equipments ANSWER DOWNLOAD EXAMIANS APP