Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Minimum float None of these Maximum float Zero float Minimum float None of these Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Deterministic activities Small projects Research and development projects Large and complex projects Deterministic activities Small projects Research and development projects Large and complex projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP