Construction Planning and Management
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

20.143 minutes
27 minutes
21 minutes
15 minutes

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in wastage of inspection costs
Reduction in costs for the removal of defects
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection

ANSWER DOWNLOAD EXAMIANS APP