Construction Planning and Management
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

27 minutes
21 minutes
15 minutes
20.143 minutes

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same
expected time of activity B is greater than the expected time of activity A
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

All listed here
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities

ANSWER DOWNLOAD EXAMIANS APP