Construction Planning and Management
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be

30 kg/tonne
50 kg/tonne
40 kg/tonne
20 kg/tonne

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the purchase of construction materials
On commencement of work at site for payment of loan taken by him
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

All listed here
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

ANSWER DOWNLOAD EXAMIANS APP