Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Loose sand Concrete Asphalt Firm earth Loose sand Concrete Asphalt Firm earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications Top level executions over work Rigid structure All listed here Extraordinary delay in communications Top level executions over work Rigid structure All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of excavation which takes 8 units of time Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 100% at the site 67% at the site and 33% under procurement 50% at the site and 50% under procurement 33% at the site and 67% under procurement 100% at the site 67% at the site and 33% under procurement 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP