Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 None of these 14 24 19 None of these 14 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 4 days 10 days 6 days 16 days 4 days 10 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Junior Engineer Engineer Assistant Engineer Executive Engineer Junior Engineer Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line and staff organization Functional organization Line organization None of these Line and staff organization Functional organization Line organization None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Change in output due to change in input Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss Change in output due to change in input Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss ANSWER DOWNLOAD EXAMIANS APP