Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 None of these 24 14 19 None of these 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Assistant Engineer Executive Engineer Engineer Junior Engineer Assistant Engineer Executive Engineer Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is true but R is false Both A and R is true but R is not the correct explanation of A A is false but R is true Both A and R is true and R is the correct explanation of A A is true but R is false Both A and R is true but R is not the correct explanation of A A is false but R is true Both A and R is true and R is the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iv) are correct (i) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 4350 kg 5515 kg 2975 kg 3425 kg 4350 kg 5515 kg 2975 kg 3425 kg ANSWER DOWNLOAD EXAMIANS APP