Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 19 None of these 14 24 19 None of these 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 0.5 0.841 1 0.999 0.5 0.841 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel Hoe Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Laying of concrete started All listed here Digging of foundation completed Digging of foundation started Laying of concrete started All listed here Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Resources Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP