Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 24 19 None of these 14 24 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 5 years 3.7 years 4.23 years 7.87 years 5 years 3.7 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 4 3 1 2 4 3 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Crash time Standard time Normal time Optimistic time Crash time Standard time Normal time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg Reduce by 200 kg Reduce by 250 kg Increase by 250 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP