Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project A
could invest in either of the two projects
should invest in project B
should invest in neither of the two projects

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its latest start time and earliest start time
its earliest finish time and latest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP