Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 24 14 None of these 19 24 14 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Economics of cost and benefits of the project Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input Economics of cost and benefits of the project Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1910 1920 1930 1940 1910 1920 1930 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has None of these Minimum float Maximum float Zero float None of these Minimum float Maximum float Zero float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Effective organization Functional organization Line organization Line and staff organization Effective organization Functional organization Line organization Line and staff organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured ANSWER DOWNLOAD EXAMIANS APP