Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 24 None of these 14 19 24 None of these 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Minimum float Zero float None of these Maximum float Minimum float Zero float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications Top level executions over work All listed here Rigid structure Extraordinary delay in communications Top level executions over work All listed here Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Site investigation started Class is being attended Sessional work completed Bus starts from Jaipur Site investigation started Class is being attended Sessional work completed Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP