Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all activities
Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

Yes, because of heavier overheads and handling cost
No, because of savings in site labour
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements

ANSWER DOWNLOAD EXAMIANS APP