Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 9 days 19 days 13 days 14 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 35 20 25 15 35 20 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Minimum cost Minimum time Maximum cost Maximum time Minimum cost Minimum time Maximum cost ANSWER DOWNLOAD EXAMIANS APP