Construction Planning and Management

Construction Planning and Management
The critical activity has

None of these
Maximum float
Minimum float
Zero float

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which one of the following represents an activity?

Curing of concrete
Setting of question paper
Excavation for foundation
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

35
25
20
15

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

3.5 and 5/6
4 and 5/6
5 and 25/36
3.5 and 25/36

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The basic action involved in sheep foot rolling is

Pressing
Vibration
Kneading
Tamping

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Critical path lies along the activities having total float

Negative
Same
Zero
Positive

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑