Construction Planning and Management The critical activity has None of these Maximum float Minimum float Zero float None of these Maximum float Minimum float Zero float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 25 20 15 35 25 20 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Vibration Kneading Tamping Pressing Vibration Kneading Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Same Zero Positive Negative Same Zero Positive ANSWER DOWNLOAD EXAMIANS APP