Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Minor projects Major projects All listed here Any project Minor projects Major projects All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 900 kg 300 kg 30 kg 1000 kg 900 kg 300 kg 30 kg 1000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Initiation of proposal Preparation of estimate Preparation of tender Survey of the site Initiation of proposal Preparation of estimate Preparation of tender Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP