Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Constraint Duration Event Float Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete Setting of question paper All listed here Excavation for foundation Curing of concrete Setting of question paper All listed here Excavation for foundation ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP