Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Event Constraint Float Duration Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line organization Line and staff organization Functional organization None of these Line organization Line and staff organization Functional organization None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Dummy Free float Constraint Event Dummy Free float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 24 19 None of these 14 24 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority ANSWER DOWNLOAD EXAMIANS APP