Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 2-3 is 7 All listed here 1-2 is 4 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 20 25 15 35 20 25 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Project duration time Resources None of these Both resources and project duration time Project duration time Resources None of these ANSWER DOWNLOAD EXAMIANS APP