Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Event Constraint Float Duration Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above Equal to X Less than X More than X Any of the above Equal to X Less than X More than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Hoe Dragline Shovel None of these Hoe Dragline Shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Negative Positive Same Zero Negative Positive Same ANSWER DOWNLOAD EXAMIANS APP