Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Duration Event Float Constraint Duration Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Class is being attended Bus starts from Jaipur Site investigation started Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Maximum Infinite Minimum Zero Maximum Infinite Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed Digging of foundation started All listed here Laying of concrete started Digging of foundation completed Digging of foundation started All listed here Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Survey of the site Initiation of proposal Preparation of estimate Preparation of tender Survey of the site Initiation of proposal Preparation of estimate ANSWER DOWNLOAD EXAMIANS APP