Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Constraint Float Event Duration Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Determines the status of each activity Adjusts automatically changes in activity progress Is a dynamic system None of these Determines the status of each activity Adjusts automatically changes in activity progress Is a dynamic system None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP