Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Float Constraint Event Duration Float Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 30 kg 300 kg 1000 kg 900 kg 30 kg 300 kg 1000 kg 900 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design ANSWER DOWNLOAD EXAMIANS APP