Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Duration Float Event Constraint Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Well blasted rock Moist loam Good common earth Wet sticky clay Well blasted rock Moist loam Good common earth Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 81 36 54 9 81 36 54 ANSWER DOWNLOAD EXAMIANS APP