Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Event Float Constraint Duration Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 30 kg/tonne 50 kg/tonne 20 kg/tonne 40 kg/tonne 30 kg/tonne 50 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Major projects Any project Minor projects All listed here Major projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP