Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Float Event Constraint Duration Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Hoe Clam shell Drag line Dipper shovel Hoe Clam shell Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Clam shell Bulldozer Dump truck Scraper Clam shell Bulldozer Dump truck ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Crash time Standard time Normal time Optimistic time Crash time Standard time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % More than 50 % 0.5 1 Less than 50 % More than 50 % 0.5 1 ANSWER DOWNLOAD EXAMIANS APP