Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Constraint Float Event Duration Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 5 and 25/36 3.5 and 5/6 4 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP