Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Constraint Event Float Duration Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Bar chart method Critical path method (CPM) Milestone chart Programme Evaluation and Review Technique (PERT) Bar chart method Critical path method (CPM) Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Infinite Minimum Zero Maximum Infinite Minimum Zero ANSWER DOWNLOAD EXAMIANS APP