Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Normal time Slow time Standard time Crash time Normal time Slow time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications All listed here Top level executions over work Rigid structure Extraordinary delay in communications All listed here Top level executions over work Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Light construction Heavy construction Private construction Industrial construction Light construction Heavy construction Private construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP