Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Vertical lines Horizontal lines Dots Crosses Vertical lines Horizontal lines Dots ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent The office area is being cleaned Site located Foundation is being dug The invitations are being sent The office area is being cleaned Site located Foundation is being dug ANSWER DOWNLOAD EXAMIANS APP