Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Float Duration Event Constraint Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Research and development projects Large and complex projects Deterministic activities Small projects Research and development projects Large and complex projects Deterministic activities Small projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Event Node All listed here Connector Event Node All listed here Connector ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 0.999 1 0.5 0.841 0.999 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established A project is divided into various activities Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP