Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Industrial construction Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Negative Same Positive Zero Negative Same Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP