Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Float Event Constraint Duration Float Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Tamping Vibration Kneading Pressing Tamping Vibration Kneading ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Same Negative Positive Zero Same Negative Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time Minimum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 35 25 20 15 35 25 20 ANSWER DOWNLOAD EXAMIANS APP