Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Constraint Duration Float Event Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves All listed here If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves All listed here If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Shortest duration Highest cost slope Least cost slope Longest duration Shortest duration Highest cost slope Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,43,750 Rs. 8,75,000 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 8,75,000 Rs. 10,50,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP