Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Duration Float Event Constraint Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Maximum Minimum Infinite Zero Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 4.23 years 5 years 3.7 years 7.87 years 4.23 years 5 years 3.7 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Positive Zero Same Negative Positive Zero Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP