Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Duration Float Event Constraint Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1930 1920 1940 1910 1930 1920 1940 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/6 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Delegation of authority Effective control at all levels All listed here Unity of command Delegation of authority Effective control at all levels All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Economics of cost and benefits of the project Comparison of profit and loss Comparison of assets and liabilities Change in output due to change in input Economics of cost and benefits of the project Comparison of profit and loss Comparison of assets and liabilities Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP