Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Event Float Constraint Duration Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 15 25 20 35 15 25 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float None of these Zero float Minimum float Maximum float None of these Zero float Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Cost of project is controlled Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled Total duration of project is reduced Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 22500 kg 12500 kg 5000 kg 10000 kg 22500 kg 12500 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP