Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Float Event Constraint Duration Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 24 None of these 14 19 24 None of these 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is All listed here A firm An agency A person All listed here A firm An agency A person ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Sheep foot rollers Tampers Smooth-wheeled rollers Vibratory rollers Sheep foot rollers Tampers Smooth-wheeled rollers Vibratory rollers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels Delegation of authority Unity of command All listed here Effective control at all levels Delegation of authority Unity of command All listed here ANSWER DOWNLOAD EXAMIANS APP