Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Event Float Duration Constraint Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 14 19 24 None of these 14 19 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 34500 Rs. 37950 Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 Rs. 31050 Rs. 50000 ANSWER DOWNLOAD EXAMIANS APP