Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Event Float Constraint Duration Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 54 36 81 9 54 36 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Large and complex projects Small projects Deterministic activities Research and development projects Large and complex projects Small projects Deterministic activities Research and development projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP