Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) All listed here CPP (Critical Path Plotted) MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Project duration time None of these Resources Both resources and project duration time Project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Deterministic activities Research and development projects Large and complex projects Small projects Deterministic activities Research and development projects Large and complex projects Small projects ANSWER DOWNLOAD EXAMIANS APP