• HOME
  • QUIZ
  • CONTACT US
EXAMIANS
  • COMPUTER
  • CURRENT AFFAIRS
  • ENGINEERING
    • Chemical Engineering
    • Civil Engineering
    • Computer Engineering
    • Electrical Engineering
    • Mechanical Engineering
  • ENGLISH GRAMMAR
  • GK
  • GUJARATI MCQ

Construction Planning and Management

Construction Planning and Management
The difference between the time avail-to do a job and the time required to do the job, is known as

Constraint
Float
Event
Duration

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

3, 4 and 5
1, 2 and 5
1, 2 and 4
1, 3 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

20.143 minutes
27 minutes
21 minutes
15 minutes

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A construction schedule is prepared after collecting

All listed here
Output of labour
Number of operations
Output of machinery

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is

1, 3, 2, 4
1, 3, 4, 2
3, 1, 4, 2
3, 1, 2, 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is

1, 2, 3, 4, 5
1, 3, 2, 4, 5
1, 2, 4, 3, 5
1, 3, 4, 2, 5

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑