Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Float Event Constraint Duration Float Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP