Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Constraint Event Dummy Free float Constraint Event Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Light construction Heavy construction None of these Industrial construction Light construction Heavy construction None of these ANSWER DOWNLOAD EXAMIANS APP