Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Duration Constraint Float Event Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 36 9 81 54 36 9 81 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect All listed here An owner An engineer An architect All listed here An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Top level executions over work Extraordinary delay in communications All listed here Rigid structure Top level executions over work Extraordinary delay in communications All listed here Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP