Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Constraint Event Float Duration Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 2 4 1 3 2 4 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 19 days 14 days 9 days 13 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Light construction None of these Industrial construction Heavy construction Light construction None of these Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method ANSWER DOWNLOAD EXAMIANS APP