Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Float Event Constraint Duration Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 4 3 1 2 4 3 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 3-4 is 8 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 2000 cum 1000 cum 1500 cum 500 cum 2000 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP