Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 13 days 14 days 19 days 9 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A ANSWER DOWNLOAD EXAMIANS APP