Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Float Duration Event Constraint Float Duration Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A firm A person All listed here An agency A firm A person All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.841 0.5 0.999 1 0.841 0.5 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Minimum cost Maximum cost Minimum time Maximum time Minimum cost Maximum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP