Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Constraint Float Duration Event Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1920 1910 1930 1940 1920 1910 1930 1940 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Dots Vertical lines Horizontal lines Crosses Dots Vertical lines Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP