Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Float Constraint Event Duration Float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Bus starts from Jaipur Site investigation started Class is being attended Sessional work completed Bus starts from Jaipur Site investigation started Class is being attended Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An architect All listed here An owner An engineer An architect All listed here An owner An engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 2975 kg 3425 kg 5515 kg 4350 kg 2975 kg 3425 kg 5515 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP