Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Constraint Float Event Duration Constraint Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves All listed here Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above Less than X More than X Equal to X Any of the above Less than X More than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey Availability of construction materials Availability of labour All listed here Site survey Availability of construction materials Availability of labour All listed here ANSWER DOWNLOAD EXAMIANS APP