Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Float Constraint Duration Event Float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 2-3 is 7 1-2 is 4 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 19 None of these 24 14 19 None of these 24 ANSWER DOWNLOAD EXAMIANS APP