Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Slow time Standard time Normal time Crash time Slow time Standard time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 50000 Rs. 37950 Rs. 31050 Rs. 34500 Rs. 50000 Rs. 37950 Rs. 31050 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 12500 kg 5000 kg 22500 kg 10000 kg 12500 kg 5000 kg 22500 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP