Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Duration Event Float Constraint Duration Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Foundation is being dug The office area is being cleaned Site located The invitations are being sent Foundation is being dug The office area is being cleaned Site located The invitations are being sent ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Top level executions over work Rigid structure Extraordinary delay in communications All listed here Top level executions over work Rigid structure Extraordinary delay in communications All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Initiation of proposal Survey of the site Preparation of estimate Preparation of tender Initiation of proposal Survey of the site Preparation of estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 9 81 36 54 9 81 36 ANSWER DOWNLOAD EXAMIANS APP