Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
On commencement of work at site for payment of loan taken by him
For all activities required to start the work at site on finalization of the contract document
For the purchase of construction materials

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project B
should invest in neither of the two projects
could invest in either of the two projects
should invest in project A

ANSWER DOWNLOAD EXAMIANS APP