Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Controlling the quantity of each material into each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the total quantity at each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the total quantity at each batch Weighing accurately, the quantity of each material for a job before mixing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Firm earth Concrete Asphalt Loose sand Firm earth Concrete Asphalt Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Optimistic time All listed here Pessimistic time Most likely time Optimistic time All listed here Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP