Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Float Duration Event Constraint Float Duration Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Rigid structure Extraordinary delay in communications Top level executions over work All listed here Rigid structure Extraordinary delay in communications Top level executions over work ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest May be longest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP