Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Same Positive Zero Negative Same Positive Zero Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP