Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Standard time Crash time Optimistic time Normal time Standard time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Only (i) is correct (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (ii) are correct (i) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP