Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Duration Constraint Float Event Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 5220 Rs. 1740 Rs. 3480 Rs. 6960 Rs. 5220 Rs. 1740 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP