Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Duration Constraint Float Event Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 3425 kg 2975 kg 4350 kg 5515 kg 3425 kg 2975 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete Setting of question paper All listed here Excavation for foundation Curing of concrete Setting of question paper All listed here Excavation for foundation ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A person A firm All listed here An agency A person A firm All listed here ANSWER DOWNLOAD EXAMIANS APP