Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Duration Float Event Constraint Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on All listed here Pessimistic time Most likely time Optimistic time All listed here Pessimistic time Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Light construction Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 50 kg/tonne 20 kg/tonne 40 kg/tonne 30 kg/tonne 50 kg/tonne 20 kg/tonne 40 kg/tonne 30 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP