Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Float Duration Event Constraint Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 81 54 36 9 81 54 36 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Effective organization Functional organization Line and staff organization Line organization Effective organization Functional organization Line and staff organization Line organization ANSWER DOWNLOAD EXAMIANS APP