Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Constraint Duration Event Float Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node greater than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Normal distribution curve None of these Beta distribution curve Poisson's distribution curve Normal distribution curve None of these Beta distribution curve Poisson's distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 3 1 4 2 3 1 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP