Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its latest start time and earliest start time
Its earliest finish time and earliest start time for its successor activity
Its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in wastage of inspection costs
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in costs for the removal of defects

ANSWER DOWNLOAD EXAMIANS APP