Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Duration Float Constraint Event Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum cost Maximum time Minimum time Maximum cost Minimum cost Maximum time Minimum time Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Updating Resource smoothening Critical path scheduling Resource levelling Updating Resource smoothening Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 250 kg Increase by 200 kg Reduce by 250 kg Reduce by 200 kg Increase by 250 kg Increase by 200 kg Reduce by 250 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Interfering float Total float Independent float Free float Interfering float Total float Independent float ANSWER DOWNLOAD EXAMIANS APP