Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Event Float Duration Constraint Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An owner All listed here An engineer An architect An owner All listed here An engineer An architect ANSWER DOWNLOAD EXAMIANS APP