Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Float Duration Event Constraint Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey Availability of labour All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 3 4 2 1 3 4 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 8,50,000 Rs. 5,75,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 6,50,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Minimum Zero Infinite Maximum Minimum Zero ANSWER DOWNLOAD EXAMIANS APP