Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Duration Constraint Event Float Duration Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command All listed here Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Preparation of estimates Initiating the procurement action of resources Preparation of specifications All listed here Preparation of estimates Initiating the procurement action of resources Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1930 1920 1910 1940 1930 1920 1910 1940 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true and R is the correct explanation of A A is true but R is false Both A and R is true but R is not the correct explanation of A A is false but R is true Both A and R is true and R is the correct explanation of A A is true but R is false Both A and R is true but R is not the correct explanation of A A is false but R is true ANSWER DOWNLOAD EXAMIANS APP