Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Float Duration Constraint Event Float Duration Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of labour Number of operations All listed here Output of machinery Output of labour Number of operations All listed here Output of machinery ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Functional organization Line organization Line and staff organization None of these Functional organization Line organization Line and staff organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP