Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 34500 Rs. 37950 Rs. 50000 Rs. 31050 Rs. 34500 Rs. 37950 Rs. 50000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Normal time Crash time Standard time Optimistic time Normal time Crash time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP