Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Crash time Normal time Standard time Optimistic time Crash time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Normal time Slow time Standard time Crash time Normal time Slow time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 15 35 25 20 15 35 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known All listed here Event Connector Node All listed here Event Connector Node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP