Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Event Constraint Duration Float Event Constraint Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Beta distribution curve Normal distribution curve None of these Poisson's distribution curve Beta distribution curve Normal distribution curve None of these Poisson's distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Crosses Dots Horizontal lines Vertical lines Crosses Dots Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 15 35 20 25 15 35 20 ANSWER DOWNLOAD EXAMIANS APP