Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started All listed here Digging of foundation completed Digging of foundation started Laying of concrete started All listed here Digging of foundation completed Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Slow time Normal time Standard time Crash time Slow time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper All listed here Excavation for foundation Curing of concrete Setting of question paper All listed here Excavation for foundation Curing of concrete ANSWER DOWNLOAD EXAMIANS APP