Construction Planning and Management The main disadvantage of line organization, is All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum time Maximum cost Minimum cost Maximum time Minimum time Maximum cost Minimum cost Maximum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 1 0.999 0.841 0.5 1 0.999 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources None of these Project duration time Both resources and project duration time Resources None of these Project duration time Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 15 35 20 25 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP