Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 10 days 8 days 15 days 9 days 10 days 8 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Crash time Optimistic time Normal time Between normal time and crash time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities which can be delayed without affecting the total float of preceding activity Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 5220 Rs. 1740 Rs. 3480 Rs. 6960 Rs. 5220 Rs. 1740 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP