Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 15 days 10 days 8 days 9 days 15 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 15 35 20 25 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP