Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 10 days 8 days 15 days 9 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 12500 kg 22500 kg 5000 kg 10000 kg 12500 kg 22500 kg 5000 kg 10000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here EF = ES + D LS = LF - D LF = LS + D All listed here EF = ES + D LS = LF - D LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has None of these Maximum float Zero float Minimum float None of these Maximum float Zero float Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Any of the above Less than X Equal to X More than X Any of the above Less than X Equal to X ANSWER DOWNLOAD EXAMIANS APP