Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 9 days 10 days 15 days 8 days 9 days 10 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Interfering float Total float Free float Duration Interfering float Total float Free float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey Availability of labour All listed here Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Issue of store equipments Instructions by the executive engineers Construction measurements Names of the casual labour Issue of store equipments Instructions by the executive engineers Construction measurements Names of the casual labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP