Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 27 minutes 21 minutes 20.143 minutes 15 minutes 27 minutes 21 minutes 20.143 minutes 15 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP