Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The office area is being cleaned Site located The invitations are being sent Foundation is being dug The office area is being cleaned Site located The invitations are being sent Foundation is being dug ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 0.5 More than 50 % 1 Less than 50 % 0.5 More than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP