Construction Planning and Management Which one of the following represents an activity? Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started All listed here Digging of foundation completed Digging of foundation started Laying of concrete started All listed here Digging of foundation completed Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Total float Interfering float Free float Duration Total float Interfering float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 15 35 25 20 15 35 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 ANSWER DOWNLOAD EXAMIANS APP