Construction Planning and Management Which one of the following represents an activity? Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 14 24 None of these 19 14 24 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An event An activity Both event and activity None of these An event An activity Both event and activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An owner An engineer An architect All listed here An owner An engineer An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Moist loam Wet sticky clay Good common earth Sand and gravel Moist loam Wet sticky clay Good common earth Sand and gravel ANSWER DOWNLOAD EXAMIANS APP