Construction Planning and Management Which one of the following represents an activity? Curing of concrete Excavation for foundation Setting of question paper All listed here Curing of concrete Excavation for foundation Setting of question paper All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved Preceding activities None of these Succeeding activities The particular activity involved Preceding activities None of these Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 34500 Rs. 31050 Rs. 50000 Rs. 37950 Rs. 34500 Rs. 31050 Rs. 50000 Rs. 37950 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority Unity of command ANSWER DOWNLOAD EXAMIANS APP