Construction Planning and Management Which one of the following represents an activity? Excavation for foundation Curing of concrete All listed here Setting of question paper Excavation for foundation Curing of concrete All listed here Setting of question paper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Dump truck Clam shell Scraper Bulldozer Dump truck Clam shell Scraper Bulldozer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Expected time Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest May be longest ANSWER DOWNLOAD EXAMIANS APP