Construction Planning and Management Which one of the following represents an activity? All listed here Setting of question paper Curing of concrete Excavation for foundation All listed here Setting of question paper Curing of concrete Excavation for foundation ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An owner An engineer All listed here An architect An owner An engineer ANSWER DOWNLOAD EXAMIANS APP