Construction Planning and Management
In resources levelling

Total duration of project is reduced
Uniform demand of resources is achieved
Total duration of project is increased
Cost of project is controlled

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in costs for the removal of defects
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs
Measurement of risks to eliminate failures

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and increasing indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float and independent float both must be zero
Independent float must be zero but free float need not be zero
Free float of the activity must be zero but independent float need not be zero
Free float and independent float both need not be zero

ANSWER DOWNLOAD EXAMIANS APP