Construction Planning and Management
In resources levelling

Cost of project is controlled
Uniform demand of resources is achieved
Total duration of project is reduced
Total duration of project is increased

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float and independent float both need not be zero
Free float and independent float both must be zero
Independent float must be zero but free float need not be zero
Free float of the activity must be zero but independent float need not be zero

ANSWER DOWNLOAD EXAMIANS APP