Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource levelling Critical path scheduling Resource smoothening Updating Resource levelling Critical path scheduling Resource smoothening ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Ice Concrete Loose sand Earth Ice Concrete Loose sand ANSWER DOWNLOAD EXAMIANS APP