Construction Planning and Management In resources levelling Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Wet sticky clay Good common earth Moist loam Well blasted rock Wet sticky clay Good common earth Moist loam Well blasted rock ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 2 1 4 3 2 1 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved None of these Succeeding activities Preceding activities The particular activity involved None of these Succeeding activities Preceding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP