Construction Planning and Management
In resources levelling

Cost of project is controlled
Total duration of project is increased
Uniform demand of resources is achieved
Total duration of project is reduced

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its earliest finish time and latest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its latest finish time and earliest start time for its successor activity
its latest start time and earliest start time