Construction Planning and Management In resources levelling Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Good common earth Sand and gravel Wet sticky clay Moist loam Good common earth Sand and gravel Wet sticky clay Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 3 1 4 2 3 1 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is based on time estimate Synthesising in concepts Is built of activities oriented programme All listed here Is based on time estimate Synthesising in concepts Is built of activities oriented programme All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP