Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to None of these An event Both event and activity An activity None of these An event Both event and activity An activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Minimum cost Maximum time Minimum time Maximum cost Minimum cost Maximum time Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP