Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Measurement of risks to eliminate failures Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Measurement of risks to eliminate failures ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 1 4 2 3 1 4 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Any project Major projects Minor projects All listed here Any project Major projects ANSWER DOWNLOAD EXAMIANS APP