Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Firm earth Loose sand Concrete Asphalt Firm earth Loose sand Concrete Asphalt ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 4,75,000 Rs. 5,75,000 Rs. 6,50,000 Rs. 8,50,000 Rs. 4,75,000 Rs. 5,75,000 Rs. 6,50,000 Rs. 8,50,000 ANSWER DOWNLOAD EXAMIANS APP