Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne 9 kg/tonne 20 kg/tonne 6 kg/tonne 2 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP