Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 13 days 9 days 14 days 19 days 13 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 9 days 8 days 15 days 10 days 9 days 8 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent Site located Foundation is being dug The office area is being cleaned The invitations are being sent Site located Foundation is being dug The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest critical activity Cheapest noncritical activity Costliest noncritical activity Cheapest critical activity Costliest critical activity Cheapest noncritical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP