Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 9 days 14 days 13 days 19 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Industrial construction Heavy construction Electrical construction Light construction Industrial construction Heavy construction Electrical construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Dragline Shovel Hoe None of these Dragline Shovel Hoe None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest May be longest May be shortest ANSWER DOWNLOAD EXAMIANS APP