Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 9 days 13 days 19 days 14 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D LS = LF - D All listed here LF = LS + D EF = ES + D LS = LF - D All listed here LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? All of these Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on All listed here Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 0.5 0.999 1 0.841 0.5 0.999 1 ANSWER DOWNLOAD EXAMIANS APP