Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 9 days 19 days 13 days 14 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Total float and independent float None of these Free float and independent float Total float and free float Total float and independent float None of these Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Wet sticky clay Moist loam Well blasted rock Good common earth Wet sticky clay Moist loam Well blasted rock ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority ANSWER DOWNLOAD EXAMIANS APP