Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 19 days 13 days 9 days 14 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and independent float None of these Total float and free float Free float and independent float Total float and independent float None of these Total float and free float Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float None of these Maximum float Minimum float Zero float None of these Maximum float Minimum float ANSWER DOWNLOAD EXAMIANS APP