Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 13 days 19 days 9 days 14 days 13 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X Equal to X Any of the above More than X Less than X Equal to X Any of the above More than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Same Positive Zero Negative Same Positive Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPA (Critical Path Analysis) All listed here MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) CPA (Critical Path Analysis) All listed here MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) ANSWER DOWNLOAD EXAMIANS APP