Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 9 days 13 days 19 days 14 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Increase of project completion time Change of critical path Decrease of project completion time All of these Increase of project completion time Change of critical path Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP