Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true A is true but R is false Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 10 days 8 days 15 days 9 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time Minimum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 900 kg 300 kg 30 kg 1000 kg 900 kg 300 kg 30 kg 1000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes ANSWER DOWNLOAD EXAMIANS APP