Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 9 days 14 days 19 days 13 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The contract documents for inviting tenders The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique ANSWER DOWNLOAD EXAMIANS APP