Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 14 days 9 days 19 days 13 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Minor projects Any project Major projects All listed here Minor projects Any project Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to None of these An activity An event Both event and activity None of these An activity An event Both event and activity ANSWER DOWNLOAD EXAMIANS APP