Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 3, 4 and 5 1, 2 and 4 1, 3 and 4 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is All listed here A person An agency A firm All listed here A person An agency A firm ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float None of these Zero float Minimum float Maximum float None of these Zero float Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X Less than X Any of the above More than X Equal to X Less than X Any of the above More than X ANSWER DOWNLOAD EXAMIANS APP