Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 9 days 13 days 19 days 14 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Bar chart method Milestone chart Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Bar chart method Milestone chart Programme Evaluation and Review Technique (PERT) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Normal time Standard time Crash time Optimistic time Normal time Standard time Crash time Optimistic time ANSWER DOWNLOAD EXAMIANS APP