Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 13 days 9 days 19 days 14 days 13 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Zero Minimum Infinite Maximum Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP