Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 14 days 13 days 19 days 9 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 36 81 9 54 36 81 9 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here ANSWER DOWNLOAD EXAMIANS APP