Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Electrical construction Light construction Industrial construction Heavy construction Electrical construction Light construction Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 50000 Rs. 37950 Rs. 34500 Rs. 31050 Rs. 50000 Rs. 37950 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Dipper shovel Drag line Hoe Clam shell Dipper shovel Drag line Hoe Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Optimistic time All listed here Most likely time Pessimistic time Optimistic time All listed here Most likely time ANSWER DOWNLOAD EXAMIANS APP