Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 14 days 9 days 13 days 19 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Preparation of estimate Survey of the site Initiation of proposal Preparation of tender Preparation of estimate Survey of the site Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Concrete Loose sand Ice Earth Concrete Loose sand Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Industrial construction Heavy construction Electrical construction Light construction Industrial construction Heavy construction Electrical construction Light construction ANSWER DOWNLOAD EXAMIANS APP