Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 14 days 19 days 13 days 9 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 15 minutes 27 minutes 20.143 minutes 21 minutes 15 minutes 27 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Loose sand Ice Concrete Earth Loose sand Ice Concrete Earth ANSWER DOWNLOAD EXAMIANS APP