Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 13 days 9 days 19 days 14 days 13 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel Drag line Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 3-4 is 8 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iii) are correct (ii) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Optimistic time All listed here Most likely time Pessimistic time Optimistic time All listed here Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Less than X Any of the above Equal to X More than X Less than X Any of the above Equal to X ANSWER DOWNLOAD EXAMIANS APP