Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 19 days 13 days 9 days 14 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X More than X Any of the above Less than X Equal to X More than X Any of the above Less than X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP