Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 14 days 9 days 13 days 19 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Total float Interfering float Free float Duration Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes All listed here MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) All listed here MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Loose sand Earth Ice Concrete Loose sand Earth Ice Concrete ANSWER DOWNLOAD EXAMIANS APP