Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 9 days 14 days 13 days 19 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 24 14 19 None of these 24 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of the very high order of quality control for the factory made components Yes, because of heavier overheads and handling cost No, because of repetitive manufacture of a number of elements No, because of savings in site labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest ANSWER DOWNLOAD EXAMIANS APP