Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 13 days 19 days 9 days 14 days 13 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time Pessimistic time Most likely time All listed here Optimistic time Pessimistic time Most likely time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1910 1940 1920 1930 1910 1940 1920 1930 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Junior Engineer Engineer Assistant Engineer Executive Engineer Junior Engineer Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme Synthesising in concepts Is based on time estimate All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate All listed here ANSWER DOWNLOAD EXAMIANS APP