Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 19 days 9 days 13 days 14 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Wet sticky clay Well blasted rock Moist loam Good common earth Wet sticky clay Well blasted rock Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 81 36 9 54 81 36 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % More than 50 % 0.5 1 Less than 50 % More than 50 % 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time All listed here ANSWER DOWNLOAD EXAMIANS APP