Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 19 days 14 days 9 days 13 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments Names of the casual labour Instructions by the executive engineers Construction measurements Issue of store equipments ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 8 days 10 days 15 days 9 days 8 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers ANSWER DOWNLOAD EXAMIANS APP