Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 19 24 14 None of these 19 24 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X Less than X More than X Any of the above Equal to X Less than X More than X Any of the above ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Line organization Line and staff organization Functional organization Effective organization Line organization Line and staff organization Functional organization Effective organization ANSWER DOWNLOAD EXAMIANS APP