Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 13 days 14 days 19 days 9 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Rate of inflation Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Rate of inflation Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D LF = LS + D LS = LF - D All listed here EF = ES + D LF = LS + D LS = LF - D All listed here ANSWER DOWNLOAD EXAMIANS APP