Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Independent float Total float Free float Interfering float Independent float Total float Free float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Dump truck Bulldozer Clam shell Scraper Dump truck Bulldozer Clam shell Scraper ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these Project progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP