Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Line and staff organization Functional organization Line organization None of these Line and staff organization Functional organization Line organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening ANSWER DOWNLOAD EXAMIANS APP