Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 14 days 19 days 9 days 13 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne 6 kg/tonne 9 kg/tonne 20 kg/tonne 2 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Preparation of estimate Initiation of proposal Survey of the site Preparation of tender Preparation of estimate Initiation of proposal Survey of the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Heavy construction Light construction Electrical construction Industrial construction Heavy construction Light construction Electrical construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is A person A firm All listed here An agency A person A firm All listed here An agency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP