Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 13 days 19 days 9 days 14 days 13 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects All listed here Any project Minor projects Major projects All listed here Any project Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Preparation of estimates Initiating the procurement action of resources Preparation of specifications All listed here Preparation of estimates Initiating the procurement action of resources Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP