Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 19 days 9 days 13 days 14 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Pessimistic time Expected time Optimistic time Most likely time Pessimistic time Expected time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/6 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Event Dummy Constraint Free float Event Dummy Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these Project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 3425 kg 2975 kg 4350 kg 5515 kg 3425 kg 2975 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP