Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 13 days 19 days 9 days 14 days 13 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Both resources and project duration time Project duration time None of these Resources Both resources and project duration time Project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct Both A and R is correct R is correct but A is not correct Both A and R is incorrect A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Free float Constraint Event Dummy Free float Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float None of these Maximum float Zero float Minimum float None of these Maximum float Zero float ANSWER DOWNLOAD EXAMIANS APP