• HOME
  • QUIZ
  • CONTACT US
EXAMIANS
  • COMPUTER
  • CURRENT AFFAIRS
  • ENGINEERING
    • Chemical Engineering
    • Civil Engineering
    • Computer Engineering
    • Electrical Engineering
    • Mechanical Engineering
  • ENGLISH GRAMMAR
  • GK
  • GUJARATI MCQ

Construction Planning and Management

Construction Planning and Management
The normal time required for the completion of project in the above problem is

9 days
14 days
13 days
19 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The constraints in case of resource smoothening operation would be

Resources
Both resources and project duration time
Project duration time
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is correct
R is correct but A is not correct
Both A and R is incorrect
A is correct but R is not correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as

Dummy
Free float
Constraint
Event

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which of the following earth moving machines has the shortest cycle time?

Clam shell
Hoe
Dipper shovel
Drag line

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The critical activity has

Minimum float
None of these
Maximum float
Zero float

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑