Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 13 days 9 days 14 days 19 days 13 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects could invest in either of the two projects should invest in project A should invest in project B should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 36 81 54 9 36 81 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Normal time Crash time Between normal time and crash time Optimistic time Normal time Crash time Between normal time and crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Strict adherence to specifications Each individual maintains functional efficiency All listed here Separation of planning and design part Strict adherence to specifications Each individual maintains functional efficiency All listed here Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP