Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 13 days 14 days 19 days 9 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Wet sticky clay Moist loam Good common earth Sand and gravel Wet sticky clay Moist loam Good common earth Sand and gravel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP