Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 13 days 19 days 14 days 9 days 13 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Concrete Loose sand Ice Earth Concrete Loose sand Ice ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float None of these Zero float Minimum float Maximum float None of these Zero float Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element ANSWER DOWNLOAD EXAMIANS APP