Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 14 days 19 days 13 days 9 days 14 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Independent float Interfering float Total float Free float Independent float Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If symmetrical, are called normal curves All listed here Having a single lump, are called uninodal curves If not symmetrical, are called skew curves If symmetrical, are called normal curves All listed here Having a single lump, are called uninodal curves If not symmetrical, are called skew curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP