Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 19 days 9 days 13 days 14 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 9 54 81 36 9 54 81 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1920 1910 1930 1940 1920 1910 1930 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If symmetrical, are called normal curves Having a single lump, are called uninodal curves All listed here If not symmetrical, are called skew curves If symmetrical, are called normal curves Having a single lump, are called uninodal curves All listed here If not symmetrical, are called skew curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 30 kg/tonne 50 kg/tonne 40 kg/tonne 20 kg/tonne 30 kg/tonne 50 kg/tonne 40 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP