Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 13 days 19 days 14 days 9 days 13 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Major projects Any project Minor projects All listed here Major projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Unity of command Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 50 kg/tonne 20 kg/tonne 40 kg/tonne 30 kg/tonne 50 kg/tonne 20 kg/tonne 40 kg/tonne 30 kg/tonne ANSWER DOWNLOAD EXAMIANS APP