Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 13 days 14 days 9 days 19 days 13 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 10 days 4 days 6 days 16 days 10 days 4 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 54 36 81 9 54 36 81 9 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line ANSWER DOWNLOAD EXAMIANS APP