Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 13 days 9 days 19 days 14 days 13 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Industrial construction Heavy construction Private construction Light construction Industrial construction Heavy construction Private construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Crash time Between normal time and crash time Optimistic time Normal time Crash time Between normal time and crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 1 0.841 0.999 0.5 1 0.841 0.999 ANSWER DOWNLOAD EXAMIANS APP