Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 14 days 19 days 9 days 13 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.999 1 0.5 0.841 0.999 1 0.5 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Avoids delays which are very common in bar charts Is an improvement upon bar chart method All listed here Provides a realistic approach to daily problems Avoids delays which are very common in bar charts Is an improvement upon bar chart method All listed here Provides a realistic approach to daily problems ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority All listed here Unity of command ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 15 minutes 27 minutes 20.143 minutes 21 minutes 15 minutes 27 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP