Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 9 days 19 days 13 days 14 days 9 days 19 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Most likely time Expected time Optimistic time Pessimistic time Most likely time Expected time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 80 and 90 85 and 75 90 and 80 75 and 83 80 and 90 85 and 75 90 and 80 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 4 days 16 days 6 days 10 days 4 days 16 days 6 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum time Minimum time Minimum cost Maximum cost Maximum time Minimum time Minimum cost Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock ANSWER DOWNLOAD EXAMIANS APP