Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities All of these Uncertainties Project progress Interdependencies of activities All of these Uncertainties Project progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Wet sticky clay Moist loam Good common earth Sand and gravel Wet sticky clay Moist loam Good common earth Sand and gravel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne 30 kg/tonne 20 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP