Construction Planning and Management Which of the following is a weakness of bar chart? Project progress All of these Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Horizontal lines Dots Crosses Vertical lines Horizontal lines Dots Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP