Construction Planning and Management

Construction Planning and Management
Which of the following is a weakness of bar chart?

Project progress
Interdependencies of activities
Uncertainties
All of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
CPM is

Is based on time estimate
Synthesising in concepts
Is built of activities oriented programme
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Construction team means

An engineer
All listed here
An architect
An owner

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The difference between the time avail-to do a job and the time required to do the job, is known as

Constraint
Duration
Event
Float

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Which of the following excavators is most suitable for digging under water?

Clam shell
Hoe
Drag line
Dipper shovel

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be

4.23 years
3.7 years
5 years
7.87 years

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑