Construction Planning and Management Which of the following is a weakness of bar chart? Uncertainties Interdependencies of activities Project progress All of these Uncertainties Interdependencies of activities Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Normal time Crash time Standard time Optimistic time Normal time Crash time Standard time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency Separation of planning and design part All listed here Strict adherence to specifications Each individual maintains functional efficiency ANSWER DOWNLOAD EXAMIANS APP