Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch Weighing accurately, the quantity of each material for a job before mixing Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Controlling the quantity of each material into each batch ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 3425 kg 2975 kg 4350 kg 5515 kg 3425 kg 2975 kg 4350 kg ANSWER DOWNLOAD EXAMIANS APP