Construction Planning and Management Which of the following is a weakness of bar chart? Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper All listed here Excavation for foundation Curing of concrete Setting of question paper All listed here Excavation for foundation Curing of concrete ANSWER DOWNLOAD EXAMIANS APP