Construction Planning and Management Which of the following is a weakness of bar chart? All of these Uncertainties Interdependencies of activities Project progress All of these Uncertainties Interdependencies of activities Project progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 8 days 15 days 10 days 9 days 8 days 15 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iii) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP