Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Optimistic time Normal time Crash time Standard time Optimistic time Normal time Crash time Standard time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Minimum Maximum Zero Infinite Minimum Maximum Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 85 and 75 80 and 90 75 and 83 90 and 80 85 and 75 80 and 90 75 and 83 90 and 80 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed Site investigation started Bus starts from Jaipur Class is being attended ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D LS = LF - D All listed here LF = LS + D EF = ES + D LS = LF - D All listed here LF = LS + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP