Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Normal time Standard time Optimistic time Crash time Normal time Standard time Optimistic time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP