Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 900 kg 30 kg 300 kg 1000 kg 900 kg 30 kg 300 kg 1000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Research and development projects Deterministic activities Large and complex projects Small projects Research and development projects Deterministic activities Large and complex projects Small projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 0.5 More than 50 % 1 Less than 50 % 0.5 More than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Updating Resource smoothening Critical path scheduling Resource levelling Updating Resource smoothening Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The office area is being cleaned Foundation is being dug The invitations are being sent Site located The office area is being cleaned Foundation is being dug The invitations are being sent Site located ANSWER DOWNLOAD EXAMIANS APP