Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 1000 kg 300 kg 30 kg 900 kg 1000 kg 300 kg 30 kg 900 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP