Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 30 kg 900 kg 1000 kg 300 kg 30 kg 900 kg 1000 kg 300 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Maximum Minimum Infinite Zero Maximum Minimum Infinite ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Connector Node Event All listed here Connector Node Event All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between None of these Total float and free float Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 7,600 Rs. 8,800 Rs. 5,000 Rs. 6,400 Rs. 7,600 Rs. 8,800 Rs. 5,000 ANSWER DOWNLOAD EXAMIANS APP