Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 300 kg 1000 kg 900 kg 30 kg 300 kg 1000 kg 900 kg 30 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Free float Constraint Event Dummy Free float Constraint Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If symmetrical, are called normal curves Having a single lump, are called uninodal curves All listed here If not symmetrical, are called skew curves If symmetrical, are called normal curves Having a single lump, are called uninodal curves All listed here If not symmetrical, are called skew curves ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP